completed

Oversight of Catalyst Circle

$7,440.00 Received
$7,440.00 Requested
Ideascale logo View on ideascale
Community Review Results (1 reviewers)
Addresses Challenge
Feasibility
Auditability
Problem:

<p>Catalyst Circle requires independent oversight.</p><p><br></p><p>A community maintained oversight of Catalyst Circle requires support to be sustainable.</p>

Yes Votes:
₳ 100,568,953
No Votes:
₳ 2,111,753
Votes Cast:
477

This proposal was approved and funded by the Cardano Community via Project F6: Distributed decision making Catalyst funding round.

  • download
  • download

Detailed Plan

–––––––––––––––––––––––––––––––––––––––––––––––––

The problem : How to maintain Community Oversight

--------------------------------------------------------------------------------------------------

The Catalyst Circle Oversight GitBook ( <https://catalyst-swarm.gitbook.io/catalyst-circle/> ) has been maintained since July 11th 2021. It documents and tracks the activities of the Catalyst Circle a initiative started by IOHK to advance governance in Project Catalyst.

At present this oversight is being maintained on a voluntary unpaid basis and takes approx 27 hours a month to complete ( see the weekly breakdown of hours worked below). This level of commitment is not sustainable in the medium term without being resourced.

--------------------------------------------------------------------------------------------------

The solution: Resourced Community Oversight documentation, tracking & communication

–––––––––––––––––––––––––––––––––––––––––––––––––

Once funded, the Catalyst Circle Oversight GitBook will improve distributed decision making within the next two Catalyst rounds by documenting, tracking & communicating the activities, discussions and decisions of Catalyst Circle thereby making it more transparent and accessible to all.

The GitBook is maintained by QA-DAO ( <https://stephen-rowan.gitbook.io/quality-assurance-dao/> ) in collaboration with Catalyst Circle and the Cardano & Project Catalyst communities. All content recorded is open source and licensed under Apache 2.0.

--------------------------------------------------------------------------------------------------

Secretary / Facilitator

This proposal is separate from the Catalyst Circle Secretary / Facilitator roles. And does not include any associated costs. All documentation and tracking described in this proposal is independent of Catalyst Circle resources.

--------------------------------------------------------------------------------------------------

Relevant experience (identifying information)

Stephen Whitenstall has 30 years' experience in organizing academic, community and business projects. He develops, maintains documentation and provides technical project management support for Catalyst Swarm.

In Fund 5 of Project Catalyst Stephen's QA-DAO (https://stephen-rowan.gitbook.io/quality-assurance-dao/) submitted a proposal "Quality Assurance DAO" in the Developer Ecosystem Challenge that was funded in August 2021.

You can support the activities of QA-DAO by becoming a GitHub sponsor <https://github.com/sponsors/Quality-Assurance-DAO> .

<https://www.linkedin.com/in/stephen-whitenstall-166727210>

--------------------------------------------------------------------------------------------------

A live record of additions to the GitBook

A live record of additions to the GitBook back end GitHub repository can be seen here ( https://github.com/Catalyst-Swarm/Catalyst-Circle/graphs/contributors?from=2021-07-11&amp;to=2021-09-01&amp;type=a).

--------------------------------------------------------------------------------------------------

Tracking the time spent on maintaining the GitBook

In order to provide a realistic estimate of resource requirements QA-DAO has been tracking the time spent on maintaining the GitBook. The raw Clockify data to 30th August 2021 can be found here ( https://github.com/Catalyst-Swarm/Catalyst-Circle-Co-ordination/blob/main/Documents/Clockify_Detailed_Report_01_01_2021-31_12_2021(1).csv).

A total of 27:40 hours have been spent to the 30th August 2021. Time was spent in July 2021 setting up the GitBook and documenting an extensive problem sensing exercise conducted by Catalyst Circle. It is estimated that a minimum of 27 hours will required to cover the current expansion of Catalyst Circle activities and initiatives.

A shift to note-taking on a proprietary platform inhibited documentation and tracking for Circle Meetings 3 and 4. More time will be allocated in September 2021 to resolve this issue.

--------------------------------------------------------------------------------------------------

Weekly Breakdown

Week beginning - Monday 12th July 2021

Event(s) - ​Circle Meeting 1 - July 12th, 2021​

Hours Worked - 06:40

Week beginning - Monday 19th July 2021

​Event(s) - Toolmakers and Maintainers problem sensing​

Hours Worked - 08:25

Week beginning - Monday 26th July 2021

​Event(s) - Toolmakers and Maintainers problem sensing​, ​Community Advisor Problem Sensing​, ​Circle Meeting 2 - July 29th, 2021​

Hours Worked - 02:58​

Week beginning - Monday 2nd August 2021

​Hours Worked - 03:24

Week beginning - Monday 9th August 2021

​Event(s) - Circle Meeting 3 - August 12th, 2021​

Hours Worked - 02:15

Week beginning - Monday 16th August 2021

​Hours Worked - 00:44

Week beginning - Monday 23rd August 2021

​Event(s) - Meeting 4 - August 26th 2021​, ​CA & vCA Rewarding Model - 27th August 2021​

​Hours Worked - 02:17​

Week beginning - Monday 30th August 2021

​​Hours Worked -00:55

Total hours to date (30th August 2021) :

27:40

–––––––––––––––––––––––––––––––––––––––––––––––––

Budget

Given the commitments outlined in the roadmap below it is estimated that :

Maintaining the documentation & Tracking Catalyst Circle activities

27 hours per month will be spent for 6 months.

A total of 162 hours at $40 an hour =

Subtotal : $ 6,480

Marketing

Communicating Catalyst Circle Oversight to the Cardano Community

Promotion, engagement and communication on Social Media (Twitter, Telegram, Youtube, Discord).

4 hours per month for for 6 months.

A total of 24 hours at $40 an hour =

Subtotal : $ 960

Total : 7,440

--------------------------------------------------------------------------------------------------

Roadmap ( Definition of success after 3, 6 and 12 months)

Prior to funding

Catalyst Circle Version 1 - July 2021 to October 2021

Documentation and tracking can be completed and is live.

3 months

Catalyst Circle Version 2 - November 2021 to January 2022

Catalyst Circle Version 2 roughly coincides with the release of Fund 6 (November 2022).

Once funded Catalyst Circle Oversight will aim to communicate its documentation and tracking via social media in order to reach a wider audience.

6 months

Catalyst Circle Version 3 - February 2022 to April 2022 (?)

If Catalyst Circle Version 3 proceeds it will roughly coincide with the release of Fund 7 (February 2022).

Documentation and tracking will be supplemented with commentary. Sponsorships will be sought.

12 months

Catalyst Circle Version 4+ - May 2022 to September 2022 (?)

In the long term any oversight should be self-sustaining and sponsorships will be sought to achieve this aim.

--------------------------------------------------------------------------------------------------

コミュニティ・アドバイザー・レビュー (1)

Comments

Monthly Reports

Here is the link to the project GitBook where Catalyst Circle v3 is being documented https://quality-assurance-dao.gitbook.io/catalyst-circle-oversight-v3/

NB The GitBook is the main "evidence" of the project's progress - it would be great if the "please share any evidence" field also included space for text, where links can be added.

Disbursed to Date
$7,440
Status
Still in progress
Completion Target
4/30/2022
Comments 0

Login or Register to leave a comment!

Here is the link to the project GitBook where Catalyst Circle v3 is being documented https://quality-assurance-dao.gitbook.io/catalyst-circle-oversight-v3/

Closing date of the project - in the last monthly report, I miscounted that it was 30th April. Actually 12th May (end of 6th meeting of Circle v3)

Disbursed to Date
$7,440
Status
Still in progress
Completion Target
5/12/2022
Comments 0

Login or Register to leave a comment!

Here is the link to the project GitBook where Catalyst Circle v3 is being documented https://quality-assurance-dao.gitbook.io/catalyst-circle-oversight-v3/

Disbursed to Date
$7,440
Status
Still in progress
Completion Target
5/31/2022
Comments 0

Login or Register to leave a comment!

Here is the link to the project GitBook where Catalyst Circle v3 is being documented https://quality-assurance-dao.gitbook.io/catalyst-circle-oversight-v3/

Disbursed to Date
$7,440
Status
Complete
Completion Target
7/15/2022
Attachment(s)
Comments 0

Login or Register to leave a comment!

Here is the link to the project GitBook where Catalyst Circle v3 is being documented https://quality-assurance-dao.gitbook.io/catalyst-circle-oversight-v3/

Disbursed to Date
$7,440
Status
Complete
Completion Target
1. In the next month
Attachment(s)
Comments 0

Login or Register to leave a comment!

The project is complete; but the team has not had time yet to complete a close out report. We aim to do this in the coming month. Ongoing documetation of Catalyst Circle continues with the F8 proposal 800305

Disbursed to Date
$7,440
Status
Complete
Completion Target
1. In the next month
Attachment(s)
Comments 0

Login or Register to leave a comment!

close

Playlist

  • EP2: epoch_length

    Authored by: Darlington Kofa

    3分 24秒
    Darlington Kofa
  • EP1: 'd' parameter

    Authored by: Darlington Kofa

    4分 3秒
    Darlington Kofa
  • EP3: key_deposit

    Authored by: Darlington Kofa

    3分 48秒
    Darlington Kofa
  • EP4: epoch_no

    Authored by: Darlington Kofa

    2分 16秒
    Darlington Kofa
  • EP5: max_block_size

    Authored by: Darlington Kofa

    3分 14秒
    Darlington Kofa
  • EP6: pool_deposit

    Authored by: Darlington Kofa

    3分 19秒
    Darlington Kofa
  • EP7: max_tx_size

    Authored by: Darlington Kofa

    4分 59秒
    Darlington Kofa
0:00
/
~0:00