What are the key milestones you need to achieve in order to complete your project successfully?
Milestone 1: Month 1: Project Planning, Setup and Platform Development (Weeks 1-4 , 20,000 ADA)
A. Milestone Outputs:
- Project plan document
- Team formation and roles definition
- Develop platform architecture and UIUX Design
- Start of Front-end programming
- Start of Back-end integration
- Integrate Cardano blockchain
- Implement user authentication
B. Acceptance Criteria:
- Comprehensive project plan
- Clear team roles and responsibilities
- UIUX Prototype
- Successful Cardano blockchain integration research
- Functional development environment (Front-end and Back-end)
C. Evidence of Milestone Completion:
- Project plan document shared with stakeholders
- Team formation and roles documentation
- UIUX Prototype demo
- Cardano blockchain integration report
- Development environment setup confirmation
Milestone 2: Month 2: Payment Gateway Integration (Weeks 5-8, 10,000 ADA)
A. Milestone Outputs:
- Integrated payment gateway (Flutterwave)
- Create African currencies wallet system
- Develop fiat on-ramp and off-ramp solutions
- Test currency conversions
- Security audit and compliance review
B. Acceptance Criteria:
- Successful payment gateway integration
- Successful African Wallet System implementation
- Fiat on-ramp and off-ramp solutions completion
- Security audit and compliance review completion
C. Evidence of Milestone Completion:
- Payment gateway integration demo
- African Wallet System demo
- Currency Conversion demo
- Security audit and compliance review report
Milestone 3: Month 3: Cardano ADA Integration (Weeks 9-12, 10,000 ADA)
A. Milestone Outputs:
- Integrated Cardano ADA wallet
- ADA payment processing implementation
- Testing and debugging
B. Acceptance Criteria:
- Functional Cardano ADA wallet integration
- Successful ADA payment processing
- Thorough testing and debugging
C. Evidence of Milestone Completion:
- Cardano ADA wallet integration demo
- ADA payment processing testing results
- Debugging logs and issue resolution documentation
Milestone 4: Month 4: Mobile and Web Applications Completion (Weeks 13-16, 10,000 ADA)
A. Milestone Outputs:
- Complete web application
- Complete mobile application (iOS and Android)
- Conduct user testing
- Deploy mobile app
B. Acceptance Criteria:
- Functional mobile and web applications
- Intuitive user interface and experience
- Compliance with design specifications
C. Evidence of Milestone Completion:
- Functional product test video
- Mobile and web application demos
- Testing and quality assurance reports
Milestone 5: Month 5: Testing and Quality Assurance (Weeks 17-20)
A. Milestone Outputs:
- Comprehensive testing plan
- Conducted unit testing, integration testing, and UI testing
- Quality assurance review
B. Acceptance Criteria:
- Thorough testing plan
- Successful testing and quality assurance
- Identification and resolution of critical issues
C. Evidence of Milestone Completion:
- Testing plan document
- Testing and quality assurance reports
- Issue resolution documentation
Final Milestone: Month 6: Launch Preparation and Deployment (Weeks 21-24, 35,000 ADA)
A. Milestone Outputs:
- Finalized launch plan
- Deployment on Cardano mainnet
- Develop marketing strategy
- Execute social media campaign
- Marketing and promotion materials
B. Acceptance Criteria:
- Comprehensive launch plan
- Successful deployment on Cardano mainnet
- Effective marketing and promotion materials
C. Evidence of Milestone Completion:
- Launch plan document
- Deployment confirmation on Cardano mainnet
- Marketing and promotion strategy and materials review